Rabu, 12 Desember 2012

MONITORING SYSTEM CATHODIC PROTECTION PIPELINES



PROTECTED PIPELINES

East - West Pipeline Runs From East To West Across Country To Transport Oil And Gas From East Part (A) To West Part (B) In Order To Supply Energy For The Many Industrial Projects and The Pipeline From North Part (C) To The South Part (D) Of The Country.

CATHODIC PROTECTION

Cathodic Protection (CP) system protects metal pipelines against corrosion.
Impressed CP system relies that Transformer Rectifiers (TR) are supplying  consistent DC current to underground anode beds. Too low TR current leads to corrosion but too high current can lead to disbonding of the pipe coating and hydrogen embrittlement. 


CP MONITORING SYSTEM

AutoLog Cathodic Protection (CP) monitoring system monitors CP Transformer Rectifier’s impressed current,  voltage and optionally pipe-to-soil  potential measurements.


CP COMMUNICATION

Cathodic Protection (CP) system sends measurement data wirelessly to nearest base station.
AutoLog Cathodic Protection system can send measurement data using the following networks:

• Conventional Radio Network
• TETRA Network
• GSM Network
• RS-485 Network
• TCP/IP Network

Base stations are connected together to form one huge communication network which covers the whole East West- and South to North pipeline areas.

CP SCADA SYSTEM

From SCADA application users can see rectifier locations on map, alarms from abnormal situations and all measurements in trend lines. Measurements and alarms  are stored in SCADA server's SQL  database. Authorized users can see SCADA application views using normal web browser anywhere within the company's  LAN network. 

Corrosion Design Engineering

Minggu, 11 November 2012

Trip Analysis System


In order to determine the root cause of an emergency shutdown of a plant caused by failure or the like, a trip analysis system can support the analysis of the failure by collecting the events and sequence data around the time when a major piece of equipment of the plant trips.
This system is offered by using components of DIASYS Netmation.

Functions

  • Post trip log function
    When a major piece of equipment of the plant trips, this function collects the data of the pre-registered analog and digital signals around the timing of the trip and prints out the data. By collecting and printing out the process data around the timing of the trip, it supports the investigation and analysis of the root cause.
  • SOE report function
    When a major piece of equipment of the plant trips, this function prints out the high-speed events and the data recorded in the event trace(Note) around the timing of the trip. By displaying the process data around the timing of the trip in chronological order in high precision, it supports the investigation and analysis of the root cause.
    (Note) Event trace
    The event trace is used to record alarm events, operations on operator stations, and logic monitoring adjustment operations. (The timestamp resolution is one second.)
  • Flight recorder
    When a major piece of equipment of the plant trips, this function collects the data of the pre-registered process values around the timing of the trip and displays the data on a trend graph.
  • Functional Specification
    Item Specification
    Post-trip log SOE report Flight recorder
    Collection period Up to 20minutes before and after a trigger Up to 30minutes before and after a trigger Up to 1minute before and after a trigger
    Collection cycle 1second(Mximum resolution) 1millisecond Minimum calculation interval of logic
    (100milliseconds is standard)
    Number of data points Up to 64points per group.
    Up to 8triggers can be set per group.
    Up to 128points per group Up to 32points per group.
    Up to 8triggers can be set per group.
    Number of groups Up to 160groups Up to 10groups Up to 4groups per MPS
 trip analysys.pdf

Rabu, 10 Oktober 2012

Mitsubishi Plant Optimization System


A Mitsubishi Plant Optimization System (MHI-POS) can calculate the efficiency of each major piece of equipment as well as the overall plant efficiency by inputting actual plant data into an efficiency calculation program.
On the other hand, the calculation result when the ideal plant data, that is the plant data at the time of the design, is input into the efficiency calculation program can be interpreted as the optimal efficiency of each major piece of equipment.
If you compare those two efficiency values, they are always different.
The actual efficiency can be lower because of things like wear and dirt on the heat exchangers.
By comparing the actual efficiency and the optimal efficiency calculated from the design data, an MHI-POS can find out where maximum efficiency drops occur in the power plant.
Therefore, if you use an MHI-POS, you can find which part of the system you should spend a limited budget on in order to improve the plant performance effectively.
MHI-POS

Functions



  • Efficiency drop display
    The actual efficiency and the optimal efficiency of a major piece of equipment can be displayed as values and bar graphs on the plant system diagram. The efficiency drop can be converted to a monetary value to be displayed as an operational loss when you compare the actual plant status and the calculated optimal status.
  • Validity of process values can be verified
    When efficiency is calculated, it is important that the process values used for efficiency calculation are precise.
    Consequently, the efficiency calculated from data received from a transmitter with large errors is not reliable.
    This system checks the validly of major process values by using consistency checks between major signals.
    For each major process value, the correlation data between the signal and the correlated signals is predefined in the system. If the process value stops satisfying this correlation, the signal is deemed unreliable and is excluded from the inputs of the efficiency calculation.
    Instead, the interpolated value calculated from the plant model is used.
  • Historical trend graph for efficiency and efficiency drops
    You can save measured process values, calculated actual efficiency, calculated optimal efficiency, and so on into a historical trend graph and view the data at your convenience. As a standard option, you can save the data of the past three years in the system, and you can compare the current efficiency values with previous values.
  • Analysis for the cause of efficiency drops
    An MHI-POS can analyze the root cause of efficiency drops.
    If the difference between the actual efficiency and the optimal efficiency exceeds the threshold, an efficiency drop alarm is generated. At the same time, the program for root cause analysis on efficiency drop automatically starts.
    The root cause analysis function uses the knowledge base of the relationship between an instance of efficiency drop and its probable cause based on the know-how and experience MHI has accumulated over many years. Triggered by an efficiency drop alarm, the condition at the time is checked against the knowledge base, and guidance about the probable causes of the efficiency drop is displayed.
    If a new type of incident not included in the knowledge base occurs, the user can update and customize the knowledge base.
MHI-POS
MHI-POS

Main Equipment calculating the optimal efficiency by MHI-POS

An MHI-POS calculates the efficiency drop for the following major pieces of equipment.
(a) Boiler
(b) Feed Water Heater
(c) Turbine Condensor
(d) Turbine
(e) Main pump

Data required for POS

An MHI-POS needs the heat balance data of the plant because it needs to calculate the efficiency for each major piece of equipment using a plant model.
If DIASYS Netmation is introduced, the necessary data for the MHI-POS can be acquired from an accessory station (ACS). In order to design an MHI-POS, the following data is necessary in addition to the data acquired from the ACS.
(a) Electric current values at the main pumps and fans
(b) Generated heat from the fuel used
(c) Fuel costs
(d) Electricity rates
(e) Others

System Configuration

An MHI-POS has the following system configuration.
System Configuration

Minggu, 09 September 2012

Joint Operation System : Control Systems

Overview
Due to recent turns of events such as electricity liberalization and deregulation, factory management has entered a new competitive era, and a factory with steam power facilities is now strongly required to operate in a more economically efficient way than ever. MHI JOINT OPERATION SYSTEM (MHI JOS) supports this trend in factory management.
In private power plants or factories with multiple boilers and turbines, in order for each boiler and turbine to operate with most economical steam and power generation, an MHI JOS performs real-time optimization calculations, displays the results, and controls each boiler and turbine accordingly.
In paper factories, iron foundries, and the like, in some cases, the boilers, turbines, and air pipes in are constructed in a complex way, and various types of fuels such as coal, fuel oil, and surplus blast-furnace gas must be burned in an efficient way. In addition, various requests regarding power demand, electricity trading, steam demand, and others have to be satisfied.
At any moment, the most economical operation pattern needs to be found based on overall evaluation of all those conditions. An MHI JOS formulates those conditions as a multivariable equation, and solves it in real time.
This is enabled by the following three functions:
(1). Economical operation solver for an n-th degree equation as a conditional non-linear optimization problem
(2). State estimation function as a countermeasure against detection error; Automatic update function for operation characteristics of each piece of equipment to compensate for changes in characteristics over time.
(3). A function to send the values of control variables to a control system such as a distributed control system (DCS) or to a direct control panel, based on the calculation result from a JOS.
Based on the vast experience as a leading plant manufacturer, an MHI JOS offers optimal operation of factory steam power and meets our customers' needs by constructing a flexible and distributed PC and server system using the latest software technology.

System Configuration


System configuration of an MHI JOS
An MHI JOS is the latest Windows-based PC that comes with realtime operation software with MHI JOS functions. You can operate an MHI JOS on an ergonomics-based operator station (OPS). The operation is based on general-purpose package software.
Functions are distributed to a JOS and a control system. Some functions need to be handled solely by the control system, and others need to be shared between the two. Functions are distributed so that, even if the MHI JOS PC fails, stable control functions over all units can be maintained with backup from the control unit.

Joint Operation System.pdf
Application MJOS.pdf

Minggu, 12 Agustus 2012

MODERN SCADA PHILOSOPHY IN POWER SYSTEM OPERATION


This paper presents SCADA concepts used mainly in power systems, as a critical infrastructure in all life sectors. New power system demands regarding energy quality and efficiency, power system load or stability has risen for system operators all around the world. The new control and monitoring strategies include better SCADA systems and new measurement systems (wide area measurement systems with synchrophasors). 
The SCADA concepts discussed in the paper were implemented at the national power system dispatcher and also, at the power plant level.   
Keywords: power system, SCADA concepts, real time monitoring, wide area measurement systems. 

1. Introduction

The current necessity for more and more energy in all the industrial sectors brings a variety of challenges for engineers involved in power system control. The requirements of a proper power system operation, as shown in [1], cannot beaccomplished without a supervisory control and data acquisition system(SCADA). 
The main objective in power systems is maintaining the balance betweenpower generation and production, assuring the reliability of the system. 
This purpose is becoming harder to achieve hence to the new renewable power sourcesthat bring new uncertainties and parameters’ variations into the power grid.Considering these aspects, is shown, one more time, the importance of monitoringsystems.
SCADA system supervises, controls, optimizes and manages generationand transmission systems. The main component of these systems are RTUs(Remote Terminal Units) that collect data automatically and are connecteddirectly to sensors, meters, loggers or process equipment. They are located near the monitored process and they transfer data to the controller unit when requested.They often include integral software, data logging capabilities, a real-time clock(RTC) and a battery backup. Most of the RTUs are time redundant. These devices are complete remote terminal units that contain all of the transceivers, encoders,
and processors needed for proper functioning in the event that a primary RTU stops working. Meter readings and equipment status reports can also be performedby PLCs (Programmable Logic Controllers).
The purpose of the paper is to show modern SCADA concepts and their links with new measurement systems that include phasor measurement units inorder to fit the complex requirements of the power system in the current context of environmental and economical challenges.

2. Challenges in modern power systems

The critical infrastructures, such as electric power systems,  telecommunication networks and water distribution networks are systems that influence society’s life. Designing, monitoring and controlling such systems is becoming increasingly more challenging as a consequence of the steady growth of their size, complexity, level of uncertainty, unpredictable behavior, and  interactions, [2]. In center of the well functioning of society lies the electric power system.
The secure and reliable operation of modern power systems in Europe represents a competitive task due to the penetration of variable renewable energy sources. Starting with the European recommendation that 20% of Europe’s energy should  be obtained from renewable sources by the year 2020, new issues occurred in power systems.

The new requirements for the electric networks are related to the different involved parameters, as shown in Fig. 1. Further, these aspects will be discussed in detail.  
A. Power system load is the main aspect to be considered for a good operation of the grid (maintaining the power balance of the system: active power production should meet consumers’ needs).
In order to maintain the load balance in the power system, generation planning and forecasting is an essential task. Generation planning usually involves centralized generation facilities with a reasonable size and with an operation that is controlled by a dispatching center. All small generation units such as microhydro.
Fig. 1. New challenges in power systems
B. The problems related to the quality of the electricity supply concerns network operators and network users (energy consumers or producers) also. Still, this issue will be handled by the system operator who is in charge of setting up the facilities that will enable the control of energy quality.
Mainly, from consumer’s point of view, power quality reduces to the continuity in power supply and the voltage characteristics.  The power supply continuity is also related to the load balance. But voltage quality is set according to its characteristics: frequency, amplitude, waveform and symmetry. These parameters should be kept into the limits accepted by the ENTSOE regulations.
C. Grid efficiency refers to a load balances in an economical and environmental manner. The main purpose is to reduce the power consumption during the peak load demand and to increase it when the load demand is low.

D. The behavior during fault conditions should be monitored and data should be stored in a historian server in order to improve system stability.
E. System adequacy represents the power system capability of matching the evolution of the power flux. The system adequacy can be considered from two points of view:
  • The capacity of the production units in the power system to cover the demand (load).
  • The ability of the transmission system to transport the power flows between the generator units and the consumers. 
F. System stability is influenced by both voltage and frequency control.
All the previous mentioned aspects are subjective to the presence of the  Distributed generation units, which are referred as decentralized plants. Most of these plants bring uncertainties into the system as they are influenced by factors other than just the electricity demand – heat requirement in the case of cogeneration units and climatic conditions when it involves wind power plants.
The additional demands for the system operator are, [3]:
- to adopt a probabilistic approach for managing the network;
- to foresee greater power flux flexibility between centralized and decentralized plants;
- to transfer most of the ancillary services to the centralized units;
- to review reactive energy compensation plans for voltage regulation;
- to ensure a clean network infrastructure to guarantee stability.
In order to increase the security of the power grid, interconnections were made  between different networks around the world. Some of these networks are being used close to their stability and security limits due to economic constraints. Under these conditions, unavoidable disturbances such as short circuits, temporary
outages or line losses can throw them outside their stability zone at any time.
These big networks with their increased power flows are becoming very complex to manage and coordinating their command and control systems is becoming problematic.
In this context, power companies in different parts of the world are therefore feeling the need for a real-time wide area monitoring system (WAMS). Network control using phasor measurements synchronized through satellites and spread over the entire network could become essential mainly to dampen the power swings between interconnected zones.

3. SCADA concepts

A SCADA control center performs centralized monitoring and control for field sites over long-distance communications networks, including monitoring alarms and processing status data. Based on information received from remote stations, automated or operator-driven supervisory commands can be pushed to remote station control devices, which are often referred to as field devices. Field devices control local operations such as opening and closing valves and breakers, collecting data from sensor systems, and monitoring the local environment for alarm conditions, [4].
Although SCADA is a widely used application in most industries, requirements within the electric utility industry for remote control of substations and generation facilities has probably been the driving force for modern SCADA systems.
Fig. 2 shows the components and general configuration of a SCADA system. The control center contains the SCADA Server (MTU) and the communications routers. Other control center components include the human machine interface (HMI), engineering workstations, and the data historian, which are all connected by a LAN. The control center collects and logs information gathered by the field sites, displays information to the HMI, and may generate actions based upon detected events. The control center is also responsible for centralized alarming, trend analyses, and reporting. The field site performs local control of actuators and monitors sensors. Field sites are often equipped with a remote access capability to allow field operators to perform remote diagnostics and repairs usually over a separate dial up modem or WAN connection. Standard and  proprietary communication protocols running over serial communications are used to transport information between the control center and field sites using  telemetry techniques such as telephone line, cable, fiber, and radio frequency such as broadcast, microwave and satellite.
The communication architectures are different depending on the implementation.
Fig. 3 shows four types of architecture used: point-to-point, series, series-star, and multi-drop. Point-to-point is functionally the simplest type; however, it is  expensive because of the individual channels needed for each connection. Series configuration reduces the number of channels used; however, channel sharing has
an impact on the efficiency and complexity of SCADA operations. The series-star and multi-drop configurations use one channel per device which results in decreased efficiency and increased system complexity.

For SCADA systems used in power grids there are specific demands (shown in chapter 2) that have to be accomplished (Fig. 4),[5]. 
Different SCADAimplementations for power systems were described in literature, [6-9].

Fig. 4. SCADA functions in a power system
A detailed view of this functions is given below:
• Supervisory control and data acquisition - Supervises the status or the changes of breakers, connectors, and protective relays; induces of charged/uncharged status of lines and buses; supervises active/reactive power against operational/emergency limit; judges network faults;
• State estimation and scheduling - Estimates most likely numerical data set to represent current network;
• Load forecasting - Anticipates hourly total loads (24 points) for a  few days ahead based on the weather forecast, type of day, etc. utilizing  historical data about weather and load;
• Power flow control - Supports operators to provide effective power flow control by evaluating network reliability, considering anticipated total load, network configuration, load flow, and contingencies;
• Data maintenance - Enables operator to modify the database of power device status and network topology by defining parameters;
• Voltage/reliability monitoring - Monitors present voltage reliability and transient stability and predicts future status some hours ahead;

4. Wide area measurement systems

Wide area measurement systems consist of advanced measurement  technology, information tools, and operational infrastructure that facilitate the understanding and management of the increasingly complex behavior exhibited by large power systems. A WAMS may be used as a stand-alone infrastructure that complements the grid’s conventional supervisory control and data acquisition
system. As a complementary system, a WAMS is expressly designed to enhance the operator’s real-time information about the parameters status,as shown in [1015]. This is necessary for a safe and reliable grid operation, [16].

Important parts in WAMS high-quality operation are the phasor measurement units (PMUs). These are devices which use synchronization signals from the global positioning system (GPS) satellites and provide the phasors of voltage and currents measured at a given plant, as shown in Fig. 5.

A phasor is a mathematical representation of a sinusoidal waveform (Fig. 6), [17]. The magnitude A is either a peak or RMS value of the sinusoid. The phase angle θ is determined by the sinusoidal frequency and a time reference. This reference is arbitrary and is generally chosen to be convenient for the particular situation. Synchrophasors are phasor values that represent power system sinusoidal waveforms referenced to the nominal power system frequency and coordinated universal time (UTC), the international time standard. The phase angle of a synchrophasor is uniquely determined by the waveform, the system frequency, and the time of measurement. Thus, with a universal precise time reference, power system phase angles can be accurately measured throughout a power system, which brings a new perspective to the electrical power system monitoring.

Fig. 6. Phasor representation of sinusoidal waveform

Most phasor measurement-based WAMS operate at 6–60 measurements/s,  which is ideal for system dynamics measurement. A large quantity of information can be obtained at these rates using PMUs, so it should be employed for system monitoring. Fig. 7 shows a wide area measurement system using PMUs and
phasor data concentrators (PDCs).

Fig. 7. Wide area measurement system using PMUs 

PMUs are considered an important technology employed by WAMS. That is the reason why they are installed and tested in different countries around the world, as seen in [18-21] and used in applications such as real time system monitoring and post disturbance analysis.

In a general manner, the PMU applications (Fig. 8) can be divided into four main domains: state estimation, protection, supervision and network control. These sections are neither mutually exclusive nor exhaustive. In fact, a measurement given by a device for the state estimator can also be used for a machine control loop or FACTS.
Fig. 8. PMU application domains

State estimation has become a critical application function for power and energy control centers. WAMS with phasor measurement avoids the problems of convergence and topology errors encountered with traditional estimation. The most commonly used phasor estimation is the discrete Fourier transform (DFT).
This technique uses the standard Fourier estimate applied over one or more cycles at the nominal system frequency. With a sufficient sample rate and accurate synchronization with UTC, it produces an accurate and functional phasor value for most system conditions. There are problems with this approach, however, such as off nominal system frequency, limited data rates, and interfering signals and studies such as [22] discuss the possibility of overcoming these issues.

The main advantage of using synchronized measurements is improving the already installed protection systems in the networks. In opposition to the currently installed systems that operate in the time scale of seconds, it takes just a few  milliseconds using synchronized measurements. System control meets progress with the usage of synchronized phasor  measurements, especially in an interconnected power system.

The introduction of phasor measuring units (PMUs) in power systems  Significantly improves the possibilities for supervising power system dynamics. A  number of synchronized phasor measurement terminals, installed in different locations of a power system provides important information about different AC  quantities e.g.voltages, currents,active and reactive power, all of them based on the same GPS time reference.

5. SCADA and WAMS for a reliable power system operation

For a reliable power system operation, the two monitoring systems  (SCADA and WAMS) have to collaborate perfectly. Data from all the components of the grid are gathered using SCADA. A state estimator can be build in order to have a view of the real time performance, as shown in [23]. It influences all the functions involved in system’s operation, as depicted in Fig. 9.  



Fig. 9. Power system operation
State estimation, as a major function in any monitoring system, has shown an improved action with PMUs. Data across the interconnected electrical system is received synchronous in the state estimation center. Fig. 10 presents a hybrid SCADA/PMU system to show the interactions between these two systems,[24]. 

Fig. 10. Power grid monitoring
6. Conclusions

The given economic, social and quality-of-life aspects and the interdependencies among infrastructures call for a modern power grid with an upgraded SCADA system.  
A continuous improvement of SCADA functions, mainly on the automatic voltage and generation control is imposed. Implementations of load frequency control, as a key component of the SCADA system in the Romanian Power System are shown in [26-31]. 
The energy management system/SCADA control center is the heart of the power system grid. Its main objective is to inform the system operator about the current state of the electrical grid and to recognize possible threats to the grid integrity. In order to avoid these risks, the state estimation function of SCADA needs to improve. One solution, presented in the paper, is the deployment of realtime phasor measurements.
They can be exploited to provide greater power system reliability.

The usage of synchronized SCADA/PMU data is one of the most powerful tools for wide-area monitoring and control since it uses current system conditions to predict potential problems ahead of time. 

R E F E R E N C E S

[1] I. Fagarasan, S. St. Iliescu, N. Arghira, Advances in Power System Control, Proceedings of the 1st Workshop on Energy, Transport and Environmental Control Applications, pp 62-71 ISBN 978-973-618-218-1, Targoviste, 2009
[2] S. Chakrabarti, E. Kyriakides, T. Bi, D. Cai, V. Terzija, Measurements get together, IEEE PEM, Vol. 7, no 1, 2009 
[3] M. Crappe, Electric Power Systems 2nd Edition, John Wiley & Sons, Great Britain, 2009
[4] K. Stouffer, J. Falco, K. Scarfone, Guide to Industrial Control Systems (ICS) Security (Final  Public Draft), USA, 2008
[5] N. Vidal, AGC Operator Training – Transelectrica project, Bucharest, 2005
[6] D. Andone, D. Merezeanu, Modern Power Plant Control Philosopies, Proceedings on the 12 International Conference on Control Systems and Computer Science, vol. I, pp 171- 177, Bucharest, 1999
[7] D. Robescu, S.St. Iliescu, I. Catana, I. Fagarasan, s.a., Controlul automat al proceselor de epurare a apelor uzate, Ed. Tehnica, ISBN 978-973-31-2335-4, 388 pag,, Bucuresti, 2008
[8] Contract de cercetare AMCSIT 174/20.06.2006, CEEX - MODUL 1, Cercetări teoretice şi experimentale asupra sistemelor expert de exploatare optimă a proceselor tehnologice de epurare a apelor uzate din staţiile de epurare orăşeneşti şi industriale, 2006-2007
[9] B.D. Guzun, Hydro power storage complex, SCADA integrated, Maintenance of Numerical Protection and Control Systems Conference, Brasov, 2005
[10] S. Skok, I. Ivankovic, R. Matica, I. Sturlic, Multipurpose architecture model of phasor data concentrator, CIGRE 2010
[11] M. Chenine, L. Nordstrom, Performance Considerations in Wide Area Monitoring and
Control Systems, CIGRE 2010 th




Sabtu, 07 Juli 2012

POWER PLANT AUTOMATIONS






Our services related to power plant automation are just impeccable and reliable. Every customer can truly rely on us for their whole power plant automation system or electric power plant automation. Our services are available on competitive prices with the back support of efficient professionals. We are one of the major manufacturers who deals in power plant automation services.

Three-Element Drum Level Control-:

In most drum level control applications, the two-element drum level control will maintain the required water /steam interface level-even under moderate load changes. However, if an unstable feed water system exists exhibiting a variable feed heater-to-drum pressure differential, or if large unpredictable steam demands are frequent, a three-element drum level control scheme should be considered as implied from the above information, this control strategy supplies control of feed-water flow in relationship to stream flow.

The performance of the three-element control system during transient conditions makes it very useful for general industrial and utility boiler applications. It handles loads exhibiting wide and rapid rates of change. Plants which exhibit load characteristics of this type are those with mixed, continuous, and batch processing demands. It also recommended where normal load characteristics are fairly steady; but upsets can be sudden, unpredictable and/or a significant portion of the load.

Feed water Control
The basic control strategy implemented is a three-element system using drum level, steam flow and feed water flow to regulate the feed water control valve. Both accuracy and stability are improved through the addition of density compensation calculations for both drum level and steam flow. Since flow measurements are typically inaccurate at low values, feed water flow is regulated only on drum level (single element control) during start up and low load operation. The transfer between single and three-element operation is of course both automatic and bump less.

Steam Temperature Control

The Super heat steam temperature control loop is straightforward, regulating the superheat spray water/air by control valve to maintain the main steam outlet temperature. For more dynamic steam temperature circuits, temperature outlet Temperature is also measured and controlled.

Furnace Pressure Control

The furnace pressure control loop regulates the ID fan inlet vanes to maintain the furnace pressure set point. The furnace pressure signal is the process variable for the furnace pressure controller/PLC, and the ID fan is operated in coordination with the FD fan. Like the FD fan, appropriate interlocking logic is provided for the ID fan inlet vane for use during starting/stopping of the fan - also per NFPA requirements.

Steam Header Pressure Control

The Steam Header pressure control system monitors the common steam header pressure to generate a load demand for each of the boilers. To provide stable control and uniform response the control system recognizes each boiler’s contribution to the steam load and its ability to respond to load demand requests.

Combustion Control
Combustion control regulates the fuel and air for the boiler, making it the most complex and important of the control loops. The fuel/air mixture must be just right under all dynamic load conditions. Too much air results in decreased efficiency, while too little air is unsafe and even less efficient. To insure the proper ratio of fuel and air, the controls incorporate both fuel/air cross limiting and O2 trim.

Power Solution


1 Unified Energy Solutions

  • Increase in combustion efficiency

  • Enables operation with optimal excess air

  • Emission limits (NOx, CO)

  • Dynamic coordination of air/fuel ratio

  • Reduced life consumption

  • Thermal stress monitoring system

  • Better dynamic performance

  • Predictive control (responsiveness)

  • Range control (stability)

  • Soot blowing optimization

  • Advanced temperature control


6 Total Plant BLR Reporting and Data Modules

  • Build hourly, shift, daily, weekly, monthly and custom operating reports

  • Print, save or page reports based on event triggers, schedule or on demand

POWER PLANT LAYOUT
Boiler Automation System

power-plants Gas & Diesel Engines

Rabu, 06 Juni 2012

Distillery Automation System


Our distillery system is the most cost effective system amongst the many other distillery system providers. It is integrated with novel techniques and has quality features which are truly reliable. We are one of the most renowned distillery system manufacturers and suppliers in India. that always strives to achieve its customer satisfaction.

Salient Features: -


  • Improves Product quality.

  • Regular quantity of product even under varying condition.

  • Eliminates production problems.

  • Control & maintain uniformity.

  • Reduces the production losses.

SIEVE BED OF DISTILLERY AND ALCOHOL PLANT

EVAPORATOR COLUMN OF ABSOLUTE ALCOHOL

Sabtu, 05 Mei 2012

Boiler Plant Automation

We provide boiler plant for different industrial uses where this is counted as the most eminent requirement. Our boiler plant automation is equipped with latest techniques and provides more prominent results. Amongst the many industrial boiler plants manufacturer and exporters from India, our company has proved itself as the major provide of boiler plant.

Industrial Boiler Control

Introduction

In the past, boilers in an industrial complex were considered a necessary evil. However today’s a business manager know this is no longer the case? Boilers are required to maintain maximum steam generation efficiency, maximum reliability, and comply with both stringent air emission and safety regulations. To achieve this goal you need modern control hardware and software. In today’s competitive market minimization or reduction of operating costs is a valid method to increase profitability. Reducing fuel expenses associated with your boilers can directly impact manufacturing costs. We have a full portfolio of solutions for the industrial power house. Boiler control is the most commonly implemented solution. We have developed a control system standard for coal-oil- and mixed-fuel-fired boilers, which allows the expertise gained from the implementation of many of the boiler control projects to be made available to our customers.

Description

The Industrial Boiler Control solution implements the following major control strategies:
  • Steam Header Pressure Control,
  • Combustion (Fuel Flow and Air Flow) Control
  • Furnace Pressure Control,
  • Feed water/Drum Level Control,
  • Superheat Temperature Control.


SCADA VIEW OF COMPLETE BOILER AUTOMATION

Rabu, 04 April 2012

SCADA WATER SYSTEM



This software provides functionality to monitor the water system via Scadapack RTUs, have ability to manage the process, checking for alarm conditions, ability to view real time data and archived data on the Trending screen, printing various reports. The software shall be developed and configured using Parijat SCADA development system which is Microsoft VB6 based non-proprietary system.
SYSTEM ARCHITECHTURE
The system includes a stand alone PC with Ethernet communication card, which will be connected to the SCADAPACK Ethernet gateway. The Ethernet gateway will be connected to ScadaPack controller with serial connection. The Scadapack controller is attached to antenna which will transmit and receive data to/from all 7 Scadapack nonintelligent controllers.

GRAPHIC DISPLAYS

Water Plan 1 and Water Plant 2
This display provide overall picture of clean water system which includes Ground Storage Tanks, Booster Pumps, Water Well #1, Water Well #2, Hydro Pressure Tank, Elevated Tank, Various Valves. Shown labels represent actual values for System Pressure, Flow Rates, Chlorine Values, Levels, and bit statuses for variety of alarm conditions.
Lift Station Plan 1 and Water Plant 2
This display provide overall picture of Lift Stations water system which includes Pumps, Check Valves, Ground Storage Tanks, Booster Pumps, Water Well #1, Water Well #2, Hydro Pressure Tank, Elevated Tank, Various Valves. Shown labels represent actual values for System Pressure, Flow Rates, Chlorine Values, Levels, and bit statuses for variety of alarm conditions.
Lift Station Plan 1 and Water Plant 2
Communication Display provides you with communication information for every PLC. Also, it provides you some details for every RTU such as Clock time, Parameters, Comm Diagnostics.
Equipment Details
This screen provide more details on Pumps and valves such as Run times, Set points, Alarm conditions, Run status, and ability to control equipment.
Communication Information Display
This display shows current comm. settings and status.
Error Messenger
This window display errors that occurred during the process. For example: Communication Error.
Report Configuration
This screen provides you select data you want to put on report. You can select different locations and different period of time to retrieve data.
Report
Report displaying data selected from report configuration screen. This report can be printed or saved as .html or .txt file.
Alarm Viwer
This screen will show all alarm conditions which are active or happened before. You can acknowledge alarms.
Trending
Trending screen will show real time or historic data for selected points. You can specify specific points from the list to monitor, and assign different colors to the points. You can resize scaling.

Sabtu, 03 Maret 2012

Safety instrumented systems for the overpressure protection of pipeline risers


Purpose

To provide guidance to OSD inspectors on pipeline riser system pressure containment, and on the overpressure protection of riser systems by means of instrumented systems which are remotely located on a normally unattended installation (NUI) or subsea.

Action

OSD inspectors should take account of the contents of this SPC when undertaking the assessment of Safety Cases and the inspection of pipeline riser systems.

Introduction

In this SPC, the term riser system means the riser itself, associated items such as the riser ESDV and bolted joints, and the adjacent (possibly fortified) pipeline section within the installation’s 500m zone.
This SPC addresses safety instrumented systems, additional to the normal process trip/ESD function, where the plant is not fully rated for the pressure to which it might be exposed in fault conditions and either (1) there is no self-acting mechanical protective system [e.g. bursting disc, relief valve] to prevent overpressure, or (2) self-acting mechanical protection is present but by itself may be inadequate in certain foreseeable circumstances [e.g. it is not sized for the worst case].
Safe Instrumented Functions (SIFs) occur in three instances; (1) a SIF which provides a layer of protection but is not alone and is not the last to act, (2) a SIF which provides a layer of protection and is the last to act, and (3) a SIF which is the only layer of protection. This SPC addresses riser systems and the safety instrumented systems (SISs) which protect them. The subject SISs would normally be of type 2, here called final safety instrumented system (FSIS), but some duty holders use alternative terms, e.g. High Integrity Protection System (HIPS) High Integrity Pressure Protection System (HIPPS), Over Pressure Protection System [OPPS], or Secondary Protection System (SPS) – secondary in the sense that this system acts after the corresponding ‘primary’ system.

Annexes

  1. Annex A gives some examples of plant configurations where remote FSIS may be a design option.
  2. Annex B provides information in respect of the design, operation and testing aspects of FSIS.

Pipelines and risers protected by HIPPS

The implementation of FSIS subsea is relatively novel. HSE is aware of only a small number of systems worldwide, some on the UKCS.

Some FSIS have been implemented in situations where the ratio between the maximum pressure threat and system rated pressure is low (e.g. less than 1.5) and the hydrotest pressure will not be breached. In such situations, there may be a relatively low risk of loss of containment, though overpressure protection is still required. However, where this ratio is higher, the unprotected risk of a loss of containment is likely to be unacceptable and protection is critical.

The critical plant protected by a pipeline FSIS is generally a high inventory import riser system, the failure of which is a major hazard, where self-acting full flow mechanical relief is impractical and it is uneconomic to fully rate the pipeline and riser to the maximum pressure (e.g. where the pipeline is so long that rating it for the maximum pressure is feasible but renders the project uneconomic), or it is not possible to fully rate the pipeline and riser.
A pipeline rupture is a major safety hazard only if it occurs near people, though a pipeline rupture is likely to cause unacceptable environmental and commercial losses. For pipeline sections remote from offshore installations, shipping activity may be minimal and unlikely to be threatened by any release. Thus only a rupture of a pipeline near an installation or at the riser itself is addressed in this SPC as only this would be an OSD matter; however, these wider issues should be addressed by the duty holder [note that in the longer term, people may have to do potentially dangerous things on or near the installation to rectify any rupture, but this is beyond the current scope].
Pipelines Safety Regulations 1996 [SI 1996/825]
  1. Regulation 6: Provision of pipeline safety systems as are necessary SFAIRP. [This would include the process trip/ESD and the FSIS.]
  2. Regulation 11(b): Operation of pipeline to be within the safe operating limits [ie the ESD system and the FSIS must restrict the pipeline pressure to within the safe operating limits in the event of any abnormal operating conditions or faults giving rise to a potential for overpressure].
Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations 1995 [SI 1995/743]
  1. Regulation 9(1)(b): Prevent the uncontrolled release of flammable or explosive substances.
Offshore Installations (Safety Case) Regulations 2005 [SI 2005/3117]
  1. Regulation 2(5)(a): SCEs to be suitable.
Note that a FSIS on one installation protecting risers on another installation is an SCE, but the practicalities of verifying such elements are not simple, particularly when the installations concerned have different operators. 

A subsea FSIS is not an SCE where it is part of the pipeline outwith 500 m of the installation because this part of the pipeline is not part of the installation [see SCR05 guidance para 85 and MAR Regulation 3(2)(f)]. A subsea FSIS is not part of a well since its function is to protect the pipeline and riser, not to contain the pressure in the well (see SCR05 Regulation 2, the definition of a well). Thus the FSIS is not part of the installation and hence not an SCE.

Safety case assessment

Any use of a FSIS should be addressed within a Safety Case, and should be assessed in the light of this SPC. Past experience indicates that assessors should ask high-level questions during every Safety Case assessment to establish (a) if any pressure containment system situated on the installation is protected against over-pressurisation by remote FSIS located subsea or on another installation, or (b) whether the installation features any FSIS which protects any remote installation(s) from over-pressurisation of a riser system. 

Once the principle of using FSIS has been demonstrated to be ALARP, the Functional Safety Assessment of the implementation is the starting point for assessment of the more detailed design. 

SMS assessment should address the operational maintenance and testing philosophies to ensure adequate availability of FSIS. Where there is more than one offshore installation involved it is necessary, in order to ensure that the SMS measures are adequate for the FSIS protective function as a whole, to consider whether the maintenance and testing philosophies included in the Safety Cases for the other installation(s) are sufficient.

Operational inspection

Riser system FSIS are particularly critical to safety of persons and should be identified for particular attention during inspection visits.
The requirements of BS EN 61511 (Refs 4-6) are considered as good practice in the UK process sector; also note that there is a forthcoming Energy Industry Council (EIC) guidance document (Ref 9) which supports the interpretation of BS EN 61511. Duty holders should demonstrably follow the recommendations for hardware and software safety integrity, or employ other equally effective means. Duty holders should comply with the safety management system requirements, as specified in BS EN 61511, which are appropriate to the SIL of the FSIS.
Topics addressed in an inspection of FSIS should include:
  1. Audit and review carried out by the duty holder and ICP.
  2. Confirmation that the duty holder is implementing a routine maintenance and proof testing schedule for both the hardware and computer software components in order to confirm availability.
  3. Confirmation that any necessary operational procedures, including any emergency procedures that are necessary in the event of a FSIS malfunction, are in place on the installation and that personnel are familiar with them.
  4. For those FSIS which are remotely located on an adjacent interconnected installation, confirmation that items a. to c. above are satisfactory. This is especially important in a situation where there is more than one duty holder involved.
  5. Confirmation of the suitability of any transport arrangements that have been put in place to secure timely access to remote FSIS locations for critical manual intervention, maintenance or testing.
In the event that an inoperative or inadequately proof-tested and maintained FSIS is identified during an inspection, appropriate enforcement action should be taken.
Well CITHPs are likely to reduce over time and eventually may fall below the pipeline or riser pressure rating, which may themselves fall due to corrosion - the FSIS proof test and inspection plan should therefore be updated as required.

References

Note – where references are made to undated documents the most recent published edition applies.

  1. BS PD 8010 Code of Practice for Pipelines: Subsea Pipelines.
  2. BS EN 14161 Petroleum and Natural Gas Industries: Pipeline Transportation Systems.
  3. BS EN 61508 Parts 1-7 Functional Safety of Electrical / Electronic / Programmable Electronic Safety Related Systems.
  4. BS EN 61511-1 Functional Safety - Safety Instrumented Systems for the Process Industry Sector – Part 1: Framework, definitions, system, hardware and software requirements. BSI
  5. BS EN 61511-2 Functional Safety - Safety Instrumented Systems for the Process Industry Sector – Part 2: Guidelines for the application of IEC 61511-1. BSI
  6. BS EN 61511-3 Functional Safety - Safety Instrumented Systems for the Process Industry Sector – Part.3: Guidance for the determination of the required safety integrity levels. BSI
  7. API RP 14 C - Recommended Practice for Analysis, Design, Installation, and Testing of Basic Surface Safety Systems for Offshore Production Platforms.
  8. HSE ALARP Suite of Guidance.
  9. Guide to the application of IEC 61511 to safety instrumented systems in the UK process industries, Engineering Equipment and Materials Users’ Association,  EEMUA 222
  10. BS EN 10418 Petroleum and natural gas industries – Offshore production installations – Basic surface safety systems.

Consultation

This SPC has been prepared jointly by OSD 3.5, HID SI3 and OSD3.4.

Contact point for further information

For further information contact OSD 3.5.

Annex A

Plant configurations where remote HIPPS may be a proposed design option

HSE may encounter design configurations as depicted in Figs 1 to 4. Applications of the type depicted in Figs. 1, 3 and 4 have already been encountered in practice.

Note that these figures are schematic only, and do not indicate where above the water line any topsides ESDV or FSIS valves are to be located.
Subsea wells with  subsea FSIS feeding directly to a manned installation, subsea pipeline/riser  not fully rated.

Fig. 1

Subsea wells with subsea FSIS feeding directly to a manned installation, subsea pipeline/riser not fully rated.
Subsea wells with subsea HIPPS feed directly to an NUI, the subsea pipeline/riser is not fully rated.

Fig. 2

Subsea wells with subsea HIPPS feed directly to an NUI, the subsea pipeline/riser is not fully rated.
Topsides piping fully rated

Fig. 3

Subsea wells feed directly to an NUI. The NUI does not have full flow relief and the NUI import pipeline is fully rated. The NUI exports to a manned installation and the NUI export riser and the import riser on the manned platform are not fully rated.
Local wells, with flowlines fully rated, feed an NUI and the NUI exports to a manned platform.

Fig. 4

Local wells, with flowlines fully rated, feed an NUI and the NUI exports to a manned platform. The NUI topsides are not fully rated. The NUI does not have full flow relief. The export pipeline from the NUI and the riser at the manned platform are not fully rated and are protected by HIPPS on the NUI.

Annex B

System design, operation and testing

Background

An internet search was conducted to identify what has been achieved in relation to subsea wells without resorting to subsea FSIS. The search found the Gyrfalcon single well development, with an initial reservoir pressure of 14752 PSI, which has the world's first 15,000 psi subsea tree. The field has a single well, is located in 885 feet of water and is tied back 2.9 miles to Shell's GC-19 Boxer facility in the Gulf of Mexico. 

Gyrfalcon came on stream in 1999. The 6 inch flowline and riser system are rated to 12,200 psi. The 5 inch i.d. riser was tested to a burst pressure above 25,000 psi. This development demonstrates that it can be reasonably practicable to use a fully rated system without resort to a FSIS.

Pressure system design considerations

Several riser system configurations are discussed below to illustrate what OSD would consider to be appropriate overpressure protection arrangements where there is a likelihood of say > 0.1 of multiple deaths of say > 10 persons in the event of a riser system rupture. These configurations are listed in a hierarchy of descending order of inherent safety; note that HSE policy is a preference for inherent safety, refer to APOSC Principle 16 and SCR05 guidance para 136. Also note the PFEER ACOP reference to MHSWR para 38 which states that ‘it is best if possible to avoid a risk altogether’, and ‘to combat risks at source’. 

The guidance to the COMAH Regulations also discusses the ‘inherently safer approach’ as an important focus. Hence, the configurations higher in the list are recommended; an ALARP demonstration should show that each inherently safer option is not reasonably practicable before an option with less inherent safety is considered. This hierarchy is based, with some modifications in the light of experience, on that suggested by HSE Pipelines Inspectors since late 2002.

Configuration 1:

Fully rated riser system designed for the worst case fault conditions in accordance with a recognised code such as BS EN 14161 (Ref 2) supported by BS PD 8010-2 (Ref 1) – i.e. the riser system design pressure at or above the maximum possible pressure (usually CITHP or pipeline maximum burst pressure). 

Adherence to such a code gives confidence that all of the forces acting on the system have been considered and that the design is conservative. A fully rated system does not require a FSIS or any other instrumented trip function for overpressure protection, though trip functions are likely to be required for other reasons.

Configuration 2:

Riser system protected by a self-acting full-flow pressure relief system (e.g. relief valve) plus an overpressure trip function set no higher than the code rating of the protected system. Note that relief valves deliver their primary safety function by different means than an instrumented function, and therefore have different failure modes from instrumented trips; this gives the combination of a process trip + RV a useful degree of diversity lacking in a solution wholly dependent on instrumented systems. 

This configuration does not require an additional FSIS, but the integrity of the process trip/ESD should formally managed as discussed in BS IEC 61511 - in practice, a very low SIL, perhaps below SIL 1, is to be expected of the process trip/ESD. Note that for pipelines and risers designed to code, a riser designed for the same rating as a pipeline will normally have a higher burst pressure, so that in this configuration the pipeline may rupture preferentially, rather than the riser, if both layers of protection fail on demand. It is understood that the Kirstin installation in Norwegian waters uses a PSV upstream of the riser ESDV (along with an SSIV which reduces the volume requiring relief).

Configuration 3:

Riser system designed to a ‘no damage’ criterion, i.e. by engineering assessment is expected not be stressed beyond yield, and not to leak, if subjected to the maximum possible pressure. The pipeline rating is no higher than the riser system rating. Overpressure protection provided by an appropriate FSIS as a backup to the process trip/ESD system is required; each system is to be capable of independently isolating the over-pressure hazard. The FSIS may have modest SIL, and the additional layers of protection listed in para 38 should be considered.

Configuration 4:

Riser system designed to a ‘no burst’ criterion, i.e. by engineering assessment a low probability of leak or rupture is expected, typically <0 .05="" 38="" a="" additional="" an="" and="" appropriate="" as="" backup="" be="" by="" capable="" each="" fsis="" have="" hazard.="" higher="" if="" in="" independently="" is="" isolating="" layers="" listed="" maximum="" may="" medium="" no="" of="" over-pressure="" overpressure="" p="" para="" pipeline="" possible="" pressure.="" process="" protection="" provided.="" provided="" rating.="" rating="" required="" riser="" should="" sil="" some="" subjected="" system="" than="" the="" to="" trip="">

Configuration 5:

The maximum possible pressure exceeds the pipeline burst pressure, but a riser rupture is not expected as it has a somewhat higher burst pressure than the pipeline. The FSIS will have a very high integrity requirement, partly to protect the pipeline for commercial and environmental reasons. Many of the additional layers of protection listed in para 38 should be provided. This configuration is considered to have poor inherent safety and should be avoided unless the riser system protection provides a substantial assurance that riser overpressure is very unlikely. It should attract attention at the safety case assessment stage and in operation. The SIL requirement of the FSIS will be very high, but any proposal for a SIL 4 FSIS should be resisted strongly as there is no precedent for any such SIL 4 function on the UKCS and so there is no evidence that the practicalities of guaranteeing such a high standard of performance in service can be dealt with; support from OSD3.5 should be sought.

Configuration 6:

Similar to Configuration 5, but with uniform pressure containment capability throughout, so that the location of any rupture is unpredictable. A FSIS will be required, and have a very high integrity requirement, partly to protect the pipeline for commercial and environmental reasons. Many of the additional layers of protection listed in Para 38 should be provided. This configuration is considered to be highly undesirable, and should attract considerable attention at the safety case assessment stage and in operation. The SIL requirement of the FSIS will be very high, but any proposal for a SIL4 FSIS should be resisted strongly as there is no precedent for such any SIL4 function on the UKCS and so there is no evidence that the practicalities of guaranteeing such a high standard of performance in service can be dealt with; support from OSD3.5 should be sought.

Configuration 7:

The riser system burst pressure is below the maximum possible pipeline pressure and rupture is probable at the riser system (e.g. where it is the weakest link, say a pre-installed riser of inadequate rating). It is considered that this arrangement is seriously flawed and should be resisted strongly – instrumentation should not be the only defence against a potentially catastrophic hazard where practicable alternatives exist (in this example, redesign of the pipeline); support from OSD3.5 should be sought.

In determining the maximum possible burst pressure of the pipeline, the specified maximum thickness and material properties of the pipeline, or more accurately, measured actual maxima on a joint by joint basis, may be used. Specified minima for the riser, or indeed measured actual minima on a joint by joint basis, could be used to determine its minimum ‘no damage’ or burst pressure of the riser system. Where the maximum possible burst pressure of the pipeline is lower than the minimum possible ‘no damage’ pressure of the riser system (i.e. configuration 3), or below the minimum possible burst pressure of the riser system by a satisfactory margin (i.e. configuration 4), it is likely that in the event of a pressure protection system failure on demand, the pipeline section (at a safe distance from the installation) would fail preferentially, rather than the riser. Where credit is taken for the corrosion allowance in these calculations, an inspection regime will be required, e.g. to demonstrate that burst strength of the riser system declines no more quickly than the CITHP or maximum possible pipeline burst pressure.

All codes require risers to be hydrotested at 1.5 x design pressure, but carrying out a hydrotest beyond 1.5 x design pressure (though not beyond yield) would raise confidence in the analysis.

Moves away from pure inherent safety can reduce CAPEX on the pipeline and riser system, but could require higher OPEX on testing and maintenance of the FSIS, plus more CAPEX and OPEX on any additional layers of protection.

In any situation where a FSIS is proposed, the SIL of that function should be formally calculated, e.g. according to the EIC guidance (Ref 9), typically based on the demand rate and the consequences of a FSIS failure to act, and will depend on the option chosen for the riser system configuration. The integrity of the process trip/ESD should be managed as discussed in BS EN 61511 and the EIC guidance, so as to provide a basis for the demand rate element of the SIL calculation of the FSIS performance standard. 

Note that if the process trip/ESD and FSIS were to fail on demand, a higher than normal pressure may reach the riser ESDV and pose an increased hazard e.g. in the event of an incident unrelated to riser overpressure protection failure (e.g. failure due to severe weather). Thus in achieving an overall ALARP solution, this may impact on overall risk to personnel by virtue of the large inventory involved; Thus an under-rated riser system may impact on the ALARP solution for topsides systems such ventilation, fire & gas detection, deluge release on gas detection, all with associated CAPEX and OPEX implications.

Whatever riser system configuration is adopted, normal operating pressure including normal excursions should be within the code rating of the entire pipeline and riser system. 

The following additional layers of protection, listed in no particular order, may require to be addressed in the overall ALARP demonstration; it is to be expected that a riser configuration with less inherent safety will require more to be implemented. A sensitivity analysis might be helpful in identifying those measures or combination of measures which produce the greatest benefit at acceptable cost.
  1. Provide for manual isolation. This may be feasible if the over-pressure hazard is from an attended location where timely intervention [e.g. by closing valves] to prevent pressure exceeding the design pressure is practicable. The time required for manual intervention should be significantly less than the time it would take for the pressure to exceed the riser system design rated pressure. This time should be subject to an appropriate human factors assessment.
  2. Protect the riser system with subsea isolation valves [SSIV]. A subsea isolation valve upstream of a critical import riser to an installation may limit the potential inventory release, reducing the consequences and hence reducing the required SIL performance of the FSIS. It should be noted that closures (whether intentional or spurious) of a SSIV or ESDV may place additional demands on the FSIS.
  3. Provide a manually operated topsides pressure relief/blowdown system for the pipeline, which can be brought into effect in the event of FSIS failure, to fulfil a protective role with respect to the riser system. The pressure relief should be upstream of the riser ESDV. Any such design would require careful consideration to ensure the riser ESDV requirements of Regulation 19 of the Pipelines Safety Regulations are complied with. Where the pressure relief/blowdown is not upstream of the ESDV, a guaranteed method of re-opening the ESDV prior to import line pack exceeding the riser rating could be used as a protective measure. HSE is not aware of the use of this method in UK waters. A variation of this could be based on a manually operated ESDV bypass but again HSE is not aware of the use of this method in UK. For the protective measures as described in this para, gas from the pressure relief/blowdown system could be disposed of via the flare system; liquids present could be a problem, though it may be acceptable to dispose of very small quantities to sea.
  4. Provide subsea relief or bursting, e.g. a specifically designed 'weak' pipeline section, although HSE is not aware of this arrangement on any UK installation.
  5. Provide means to avoid blockages [e.g. hydrates], which will reduce the number of demands on the over pressure protection systems.
  6. Provide contingency plan for FSIS failure [e.g. evacuate the installation].

HIPPS Design

A FSIS for protecting pipeline/risers from well pressure is conceptually simple. The source of pressure, i.e. CITHP, is isolated when overpressure is detected. Depending on SIL requirement, multiple isolation valves and multiple sensors (e.g. either 1 out of 2 or 2 out of 3 voting) may be required to meet the required availability and the architectural constraints of BS IEC 61511.

Fig 4 illustrates a conceptual structure which meets SIL 3, but note that in practice the pressure transducers may be located differently, e.g. one or two may be between the shut-off valves, and that there may be other valves to allow ancillary functions (in addition to the main overpressure protection function) such as testing, flushing, manual isolation, and the safe blowdown of any locked-in inventories. The pressure transducers may be of diverse types, including a non-intrusive type.

HIPPS schematic

It should be noted that API Recommended Practice 14 C (ref 7 Appendix A - Process Component Analysis para. A.1.2.2.1) prescribes that a single shut down valve with a single independent pressure sensor and relay is an acceptable alternative to a pressure relief valve for pipeline protection, depicted in Fig A-1.3 of API RP 14C. This arrangement cannot achieve a high SIL and cannot meet the architectural constraints required by BS EN 61511 for high SILs. However, the arrangement may be considered where a low SIL is acceptable. Note that the risk based methodology of BS EN 10418:2003 (ref 10) calls for the application of BS EN 61511 in the specification of instrument-based secondary overpressure protection systems.

It is recommended that the FSIS shut down valves be dedicated to the FSIS function; certainly, credit for shut off functionality (whether automatic or manual) should be taken only once per valve – e.g. it is not legitimate to take credit in the FSIS SIL calculation for the same valves which are part of the wellhead ESD function.

The integrity required for an FSIS function is determined by the ALARP principle, overall risk targets, and engineering judgement. Considerations of ALARP and target SIL for a FSIS require difficult judgements of tolerable risk, how to partition risk reduction across other layers of protective functionality, safety benefits and costs. The cost of instrumented protective functions increases rapidly with integrity level, but at the same time the benefit in terms of further risk reduction reduces because a large proportion of the uncontrolled risk has already been protected. (Note that well CITHP may decline very rapidly, and this will have an impact on the benefit element of ALARP calculations). An ALARP case should consider both the CAPEX savings and the OPEX costs arising from the use of FSIS. What is clear that a simple calculation will not suffice for high consequence low probability events such as the rupture of a riser; QRA is recommended, along with professional judgement and current good practice as defined in this document. If the resulting required SIL is higher than 3, the overall required risk reduction should be redistributed across other measures – it is the view of HID OSD that a SIL higher than 3 calls into question the validity of the basic design concept, and that SILs higher than 3 cannot be assured in practice.

Furthermore, to achieve higher SILs there would be a need for increased testing and maintenance. Where required, this intervention can itself have a detrimental risk impact because of the need for additional helicopter flights, work on an NUI, or work subsea. 

Calculation of the SIL achievable by a FSIS appears to be a deceptively simple matter based on reliability data, though this is sparse and subject to some uncertainties. There is a problem with common cause failure, e.g. hydrate formation in the valves. 'Beta factors' used to quantify the likelihood of common cause failure mechanisms are at best uncertain. Note that the FSIS uses the same technology as the primary instrumented trip, so that these two layers of protection will always have common cause failure mechanisms which need to be addressed.
 
Note that for a FSIS to be effective, it must operate sufficiently rapidly to prevent overpressure. Often the line pack time is measured in hours, where this is unlikely to be a practical issue, but there are cases where the FSIS is required to close more rapidly (e.g. a liquids pipeline), and the required closure time should be calculated and accommodated in the design; facilities to measure closure time with sufficient accuracy should also be incorporated, especially where the required closure time is short. Note that hydraulic hammer may be an issue with rapid valve closure.

It is important to design the FSIS such that it defaults to a state of least danger on fault conditions where this property is easily designed-in (e.g. failure detected by electronic self-test), as well as to design for failure to safety on electric power failure and hydraulic power failure - thus e.g. spring return shut off valves are recommended. 

A difference between traditional subsea control and topsides control is that some solenoid valves used in subsea control use pulses of power to switch between two stable states, and so do not fail safe on loss of electrical power. It is recommended that the overall FSIS function be designed to fail safe rapidly on loss of electrical power or electrical control signal to the subsea HIPPS, so fail safe solenoid valves are preferred.

A hydraulic dump valve to speed up 'failure to safety' on loss of hydraulic power supply should be considered, as otherwise valve closure could take a long time while hydraulic fluid flows back to the supply. 

The basic function of the remote FSIS (whether subsea or on a NUI) should be autonomous, with no inhibit facility; there may be advantages in latching the tripped state. 

The basic FSIS function logic solver should preferably be non-programmable. If the target integrity for the FSIS function is SIL3 and a programmable logic solver is proposed, then whatever combination of software lifecycle specification, design, programme coding, verification and validation techniques have been used, that combination should demonstrably, reliably and reproducibly have resulted in software compatible with SIL3 performance, i.e. that software methodology is mature, widely used and with extensive field evidence, and conforms with BS 61508.

There are certain ancillary functions which are likely to be useful, though such functions should be designed so that they are not capable of interfering with the basic function of the FSIS. For example, the relevant installation(s) may have read-only supervisory communications; typically, this function should be able to read pressures and valve positions (including bypass valves, methanol injection valves), etc.

There may not be a pressure transmitter upstream of the import riser ESDV; thus in the event of an ESDV closure, the only means of determining pipeline pressure may be from subsea data transmitted by communications link. Where this comms link fails, the data will become unavailable and the status of pipeline and riser system protection would be unknown. Hence there will generally be merit in an autonomous well/manifold ESD trip after a 'time-out' in the event of a communications failure.

It may be desirable to have a trip function capable of being operated from the protected (host) installation, a FSIS reset function, and a function to force any component (e.g. pressure transmitter) to the safe state; there is no objection to implementing these ancillary functions in programmable logic. 

Start up bypass valves can be required to bleed down locked-in pressure, or to reduce the differential pressure across the FSIS shut off valves. Control of start up bypass valves around FSIS valves should be interlocked so that FSIS protection cannot be lost.

Other useful ancillary functions include valve position checks and discrepancy checks between pressure transmitter readings.

Operational testing and maintenance of HIPPS

Because of the difficulty and risks associated with personnel access to the types of remote FSIS being considered, certain SMS issues are especially relevant. In particular, remote monitoring of operational performance, demand rate and component failures should be carefully considered as part of the design. 

A properly developed strategy should be in place to cater for severe problems such as transmitter failure, loss of communications or loss of a test facility such as valve position indication. There may be advantages in employing additional redundancy so that the fault tolerance criterion continues to be met under chosen fault conditions. 

Subsea transmitters cannot normally be calibrated in situ (calibration normally involves checks at e.g. 0%, 20%, 100% of range, both rising and falling, to check for linearity, hysteresis, repeatability etc), but proof/bump tests of sufficient accuracy, at the set point, should be carried out.

Periodic partial closure tests of FSIS valves address the control circuit, solenoid valve and some failure modes of the FSIS valve itself, and so have useful diagnostic coverage, perhaps of order 50%. However, partial closure tests do not confirm that the valve will close fully, nor the stroke time for that operation, nor the leak rate in the closed state; it is therefore necessary for some periodic tests to involve full closure. An automated regime may be the only practical way to confirm correct operation. These restrictions should be considered in the reliability calculations.

Where the HIPS valve closure time requirement is rapid, this time needs to be measured accurately, and any loss of performance managed.

The required HIPS valve leakage rate should be specified, and measured on full closure test; any loss of performance should be managed.

Any maintenance of a subsea FSIS is likely to need ROV or diver intervention. Thus as many components, or whole modules, as reasonable should be diver/ROV replaceable. Instrument isolation valves should be considered for pressure transmitters, even though they result in a greater potential for failure.